Bond Newsletter April 2019

Updated on Wed, 05/01/2019 - 4:25pm

 


STEM Lab staff examine progress on an expansion to the building during an April construction tour.

STEM Lab staff gets sneak peek as construction project reaches final stretch

Two-year project remains on pace for August 2019 completion


school building

Bond improvements start at Legacy High School

The first of multiple summers of planned bond work at Legacy High School got off to an early start this spring.

Grading work began in April for the installation of a new, lighted, multi-purpose artificial turf field to replace an existing grass soccer practice field. The 2016 BondProgram prioritized the installation of artificial turf practice fields at each of the district's five comprehensive high schools as a lower maintenance alternative to traditional turf fields that also lessens district water usage.


school building

Annual bond update mailer keeps community informed on investments

The 2016 Bond Program annual community update mailer was delivered to mailboxes in April.

The report - designed to keep district families and community members informed of how their investment in Five Star Schools is making a difference in the lives of students - features a look back at completed work and also previews bond work ahead in Summer 2019. Click on the headline link above to view an online version.


Long Range Planning Advisory Committee Meeting

9 to 10:30 a.m., Thursday, May 16, 2019

Educational Support Center, 1500 E. 128th Ave., Thornton, CO, 80241

Recent News

Bond projects planned for Summer 2020

Thursday, February 27, 2020 - 10:30am

Improvements to continue at district schools, facilities

Summer 2020 will be another busy season of bond work in the Five Star District with 20 projects planned at schools and facilities across the district.

Planned work includes critical building systems improvements including plumbing repairs and mechanical systems such as building HVAC; safety and security improvements such as replacement and installation of digital security cameras, ...

FutureForward construction trudges on through weather

Thursday, February 27, 2020 - 9:45am

Construction remains on schedule despite cold, wet weather

Construction moved forward on the FutureForward at Washington Square construction site in February despite a prolonged spate of cold weather and moisture.

Work on concrete slab pours as well as the installation of the building roof were both slowed down in February but construction of the building remained on schedule to open for the 2020-2021 school year.

...