Bond Newsletter - January 2018

Updated on Wed, 10/24/2018 - 11:39am

 

 

Construction moves briskly on STEM Lab renovation

First phase of two-year renovation project on target for summer finish


Construction on new Thunder Vista P-8 in Broomfield keeps pace in January

The new Thunder Vista P-8 in Broomfield is now less than eight months away from welcoming its first students.

The rapid pace of work inside and outside the new 142,000 square-foot building is indicative of the fact that the opening of the school gets closer each day.


First month of Arapahoe Ridge expansion construction complete

Bouts of cold, snowy weather could have put a damper on the first month of construction on the Arapahoe Ridge Elementary expansion in Westminster but, other than plenty of mud to navigate around, construction kept moving in January.

The main construction activity over the past month was the excavation of the spot where the two-story, 18,900 square-foot addition will be built. With that work done, the focus shifted toward the drilling of 75 foundational piers or caissons. 


Cotton Creek expansion moving forward after water slows work

Water wreaked havoc on the first month of construction on the expansion of Cotton Creek Elementary in Westminster.

When construction crews excavated the massive hole on the northwest corner of the school to begin foundation work, they found the water table was higher than anticipated. The discovery prompted three tedious weeks of pumping water out of the hole and looking for a permanent solution to get foundation work going. 


First bond improvements take place at Horizon High School

The first of two years worth of bond improvements planned at Horizon High School got under way over the recent winter break.

Aging wooden stairs and ramps to five mobile classrooms, located on the east side of the school campus, were replaced with aluminum stairs and ramps. The stairs and ramps, original to the installation of the mobile classrooms - had began to deteriorate and cause a safety hazard.


  • Northglenn Middle School Design Advisory Group Meeting
    9 to 10:30 a.m., Wednesday Feb. 7, 2018
    Northglenn Middle School
  • Centennial Elementary Design Advisory Group Meeting
    3 to 4:30 p.m., Wednesday Feb. 7, 2018
    Centennial Elementary School, Broomfield
  • Coffee with the Thunder Vista P-8 Principal
    9 to 10 a.m., Friday, Feb. 9, 2018
    Parkside Community Center, Broomfield
  • Long Range Planning Advisory Committee Meeting
    9 to 10:30 a.m., Thursday, Feb. 15, 2018
    Educational Support Center,  1800 E. 128th Ave., Thornton, CO, 80241

Recent News

Bond projects planned for Summer 2020

Thursday, February 27, 2020 - 10:30am

Improvements to continue at district schools, facilities

Summer 2020 will be another busy season of bond work in the Five Star District with 20 projects planned at schools and facilities across the district.

Planned work includes critical building systems improvements including plumbing repairs and mechanical systems such as building HVAC; safety and security improvements such as replacement and installation of digital security cameras, ...

FutureForward construction trudges on through weather

Thursday, February 27, 2020 - 9:45am

Construction remains on schedule despite cold, wet weather

Construction moved forward on the FutureForward at Washington Square construction site in February despite a prolonged spate of cold weather and moisture.

Work on concrete slab pours as well as the installation of the building roof were both slowed down in February but construction of the building remained on schedule to open for the 2020-2021 school year.

...