Bond Newsletter - September 2018

Updated on Thu, 02/28/2019 - 3:51pm

 

video

Look back at a busy summer of bond work

Dozen projects deliver on bond promise of safer, updated schools


school building

Ribbon cuttings celebrate completion of three large bond construction projects

With construction complete, September was a chance to celebrate three bond construction projects that a met a bond goal of increasing space for students.

Ribbon cutting ceremonies took place at the new Thunder Vista P-8 in Broomfield as well as at Arapahoe Ridge and Cotton Creek elementary schools in Westminster, where both schools were expanded to eliminate mobile classrooms.

  • Thornton Elementary Design Advisory Group Meeting
    9 to 10:30 a.m., Tuesday, Oct. 2
    Thornton Elementary, 991 Eppinger Blvd, Thornton
  • Eagleview Elementary Design Advisory Group Meeting
    9 to 10:30 a.m., Wednesday, Oct. 3
    Eagleview Elementary, 4601 Summit Grove Parkway, Thornton
  • Skyview Design Advisory Group Meeting
    11:15 a.m. to 12:30 p.m., Wednesday, Oct. 3
    Skyview Elementary, 5021 E. 123rd Ave., Thornton
  • Long Range Planning Advisory Committee Meeting
    9 to 10:30 a.m., Thursday, Oct. 18
    Educational Support Center, 1500 E. 128th Ave., Thornton, CO, 80241

Recent News

Walls go up on FutureForward campus construction

Wednesday, November 27, 2019 - 8:45am

New CTE campus expected to open in 2020-21 school year

Construction on the FutureForward at Washington Square took a large, visible step forward in November.

The 67 massive, pre-cast concrete panels for the high-bay learning spaces that will house diesel automotive, welding and construction programs were installed throughout the month of November. Construction in the month of December will included the pouring of concrete slabs and the ...

School Connectivity Project construction nears 50-mile mark

Friday, October 25, 2019 - 10:45am

Project expected to be completed in Spring 2020

Construction of the main backbone for a new fiber network for the Five Star School District is more than halfway complete and on schedule for a Spring 2020 completion.

Construction work on the district’s School Connectivity Project - a new district-wide dark fiber network identified as part of the 2016 Bond Program - began in August 2018. Dark fiber refers to a ...