Construction moved forward on the FutureForward at Washington Square construction site in February despite a prolonged spate of cold weather and moisture.
Work on concrete slab pours as well as the installation of the building roof were both slowed down in February but construction of the building remained on schedule to open for the 2020-2021 school year.
By the end of the month, construction workers had taken advantage of a break in poor weather to pour the second level concrete slab and begin enclosure work near the planned front entrance of the building.