Arapahoe Ridge Elementary School

13095 Pecos Street, Westminster, CO, 80234 - 720-972-5740 - Website
arapahoeridge_august18
Project rating - 2 $5.4-$6.3M
Project rating - 2

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Construction Start Year(s) 

2017: Design Work
*Some minor improvements, including work related to instructional upgrade purchases, may occur during 2017.

2018: Major construction expected to start in early 2018 with anticipated completion for the start of the 2018-19 school year - COMPLETED

2022: Roof replacement 

 

Building Structure

  • Repair building structure and systems in the crawlspace - COMPLETED SUMMER 2018
  • Replace roof (2022)

Building Interiors

  • Repair, restore or replace failing bathroom partitions - COMPLETED SUMMER 2018
  • Replace carpet in failing locations - COMPLETED SUMMER 2018

Equipment & Furnishings

  • Replace playground for greater safety and ADA accessibility - COMPLETED SUMMER 2018

Building Systems / Safety & Security

  • Install digital security camera system - COMPLETED SUMMER 2018

Capacity / Overcrowding

  • Build addition to replace mobiles and increase classroom space - COMPLETED SUMMER 2018

Early Childhood Education

  • Expand learning opportunities for students ages 3-5 - COMPLETED SUMMER 2018

Renovations & Remodels

  • Repair or replace specials (music, art, gym) program components such as wall panels, ceiling tiles, flooring and program specific equipment - COMPLETED SUMMER 2018

Instructional Upgrades

  • Mounted digital projectors and classroom audio systems in the majority of classrooms - COMPLETED SUMMER 2018