Project rating - 1 $1.1-$1.3M
Project rating - 1

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

Federal Heights Elementary received significant renovations and improvements in Summer 2018 as part of the 2016 Bond Program.

Work that took place this summer included security camera system replacement and upgrades, building clock system replacement, plumbing repairs and upgrades, interior renovations including interior paint, new gym equipment and art room upgrades, and new electronic card readers for staff building access. 

The school will receive a new roof in 2022.

Construction Start Year(s) 

Summer 2018/Summer 2019: All proposed work listed below in building structure [minus replacing the roof], equipment & furnishings, building systems/safety & security, early childhood education, and renovations & remodels

2021: Roof replacement as listed below in building structure

*Timeline for Instructional Upgrades is dependent on the specific upgrades selected by our school community. More information to follow.

Architect: Bennett Wagner Grody Architects | CannonDesign 

Contractor: Taylor Kohrs

Building Structure

  • Replace roof - 2022
  • Repair, patch and paint exterior doors and windows to extend service life - COMPLETED SUMMER 2018

Equipment & Furnishings

  • Upgrade playground for safety, code compliance, drainage and ADA accessibility 

Building Systems / Safety & Security

  • Improve cafeteria/kitchen plumbing components - COMPLETED SUMMER 2018
  • Replace deteriorating sewer system components - COMPLETED SUMMER 2018
  • Update central electronic timing/clock system to ensure effective safety, security, bell schedule, irrigation, and heating and cooling schedules - COMPLETED SUMMER 2018
  • Install digital security camera system - COMPLETED SUMMER 2018

Early Childhood Education

  • Expand learning opportunities for students ages 3-5 - COMPLETED SUMMER 2017

Renovations & Remodels

  • Repair or replace specials (music, art, gym) program components such as wall panels, ceiling tiles, flooring and program specific equipment - COMPLETED SUMMER 2018

Instructional Upgrades

  • Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety and security upgrades, and specials/electives.