Horizon High School

5321 E. 136th Avenue Thornton CO 80602 - 720-972-4400 - Website
Horizon Building 2016
Project rating - 1 $6.4-$7.5M
Project rating - 1

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

The first phase of bond construction work in Summer 2018 at Horizon High School focused on building structure improvements including critical repairs and restoration of the school crawlspace, security camera system replacement and upgrades, replacement of chillers and associated upgrades to air handlers and pumps and replacement of bleachers in the main gymnasium.

A second phase of renovation work is planned for Summer 2019. 


News Updates

Architect selected for Horizon High School bond renovations - September 2017


Construction Start Year(s) 

2018 - Phase I - Proposed work identified below in building structure, building interiors, building systems/safety & security, and renovations & remodels - COMPLETED -

2019 - Phase II - Proposed work identified below in building structure, building interiors, building systems/safety & security, and renovations & remodels as well as turf work listed below in school grounds

*Timeline for Instructional Upgrades is dependent on the specific upgrades selected by our school community. More information to follow.


Project Team:

Architect: LOA Architecture

Construction Manager/General Contractor: Mark Young Construction

Building Structure

  • Repair building structure and systems in the crawlspace - COMPLETED SUMMER 2018
  • Replace access stairs and ramps to mobile classrooms - COMPLETED FALL 2017
  • Repair, patch and paint exterior doors and windows to extend service life

Building Interiors

  • Replace failing flooring in critical locations

Equipment & Furnishings

Replacement of bleachers in main gymnasium  -  COMPLETED SUMMER 2018

Building Systems / Safety & Security

  • Move electrical service from irrigation pit for safety -  COMPLETED SUMMER 2018
  • Upgrade heating and cooling systems for efficiency and more consistent temperature control for comfort - COMPLETED SUMMER 2018
  • Upgrade emergency response system - work integrated Brighton Horizons Pre-K with rest of building security system - COMPLETED SUMMER 2018
  • Improve security camera system

School Grounds

  • Upgrade one existing field to artificial turf for increased student use and decreased water and maintenance requirements.

Renovations & Remodels

  • Remodel priority items, such as ceilings, walls, floors, windows, doors, painting upgrades, paving restoration, lunch rooms, classrooms and bathrooms *Significant Renovation
  • Repair or replace arts program items such as easels, pottery wheels, kilns, drafting/drawing stools, airbrush stations, group work stations and A/V systems
  • Repair or replace theater and music program items such as instrument storage, practice rooms, risers & platforms, acoustic enhancements, auditorium components and A/V systems
  • Significant renovations to Five Star Stadium to address safety and ADA accessiblity impacting all high schools

Instructional Upgrades

  • Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.