Hulstrom K-8

11551 Wyco Drive, Northglenn, CO, 80233 - 720-972-5400 - Website
Hulstrom building
Project rating - 1 $2.4-$2.9M
Project rating - 1

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

Bond improvement work at Hulstrom is taking place in Summer 2019. 

Work includes:

  • Renovations to the school playground
  • All general education classrooms and the Library Media Center will be updated with new interactive technology (interactive whiteboard, amplification speaker system, and projectors).

Construction Start Year(s) 

2019: Playground work as listed below in equipment & furnishings

2020: All proposed work listed below in building structure [minus roof and skylight replacement], building systems/safety & security, and renovations & remodels

2021: Roof and skylight replacement as listed below in building structure

*Timeline for Instructional Upgrades is dependent on the specific upgrades selected by our school community. More information to follow.


Project Team

ArchitectRB+B Architects (playground improvements)

Construction Manager/General Contractor: Adolfson & Peterson Construction (playground improvements)

Building Structure

  • Repair building structure and systems in the crawlspace
  • Replace failing skylight systems
  • Replace roof
  • Seal exterior brick locations to prevent water intrusion
  • Repair, patch and paint exterior doors and windows to extend service life

Equipment & Furnishings

  • Replace playground for greater safety and ADA accessibility

Building Systems / Safety & Security

  • Replace deteriorating sewer system components
  • Replace failing water lines
  • Upgrade school intercom system to meet safety requirements
  • Install digital security camera system

Renovations & Remodels

  • Repair or replace arts program items such as easels, pottery wheels, kilns, drafting/drawing stools, airbrush stations, group work stations and A/V systems
  • Repair or replace music program items such as instrument storage, practice rooms, risers & platforms, acoustic enhancements, auditorium components and A/V systems

Instructional Upgrades

Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.