Stukey Elementary School

11080 Grant Drive, Northglenn, CO, 80233 - 720-972-5420 - Website
Stukey Building
Project rating - 3 $2.1-$2.5M
Project rating - 3

Complete - New and improved! We're excited to say, your investment plan is now complete. This process was a collaborative effort. With your help, we're engaging and inspiring all students to innovate to achieve and succeed in a safe environment.

Latest Updates

Stukey Elementary received significant renovations and improvements in Summer 2018 as part of the 2016 Bond Program.

Planned work includes a combination of more than $2 million in critical building system and infrastructure improvements (such as replacement improvements to building plumbing systems, exterior classroom window replacement, new permanent classroom walls as well as safety and security upgrades) to priorities identified through the Design Advisory Group process (such as new tubular daylighting in classrooms, addition of windows in school cafeteria, new interior paint and improvements to specials programs).


Construction Start Year(s) 

2017: Design Work
*Some minor improvements, including work related to instructional upgrade purchases, may occur during 2017.

2018: Major construction expected to take place in Summer 2018 with anticipated completion for the start of the 2018-19 school year.


Project Team

ArchitectCuningham Group Architecture

Construction Manager/General Contractor: Adolfson & Peterson Construction

Building Structure

  • New tubular daylighting devices in classrooms and library - COMPLETED SUMMER 2018
  • Exterior classroom window replacement throughout building - COMPLETED SUMMER 2018
  • Add windows to cafeteria (currently no windows) - COMPLETED SUMMER 2018

Building Interiors

  • Replace failing moveable partitions in classrooms with permanent walls - COMPLETED SUMMER 2018
  • Remove failing rubber flooring in gym with district standard poured-in-place flooring - COMPLETED SUMMER 2018
  • Replace failing flooring in school corridors and bathrooms - COMPLETED SUMMER 2018
  • New interior paint - COMPLETED SUMMER 2018
  • Painting of cafeteria walls - COMPLETED SUMMER 2018
  • Remove abandoned classroom unit ventilators to allow more teaching space - COMPLETED SUMMER 2018

Equipment & Furnishings

  • Replace kitchen grease interceptor - COMPLETED SUMMER 2018
  • Fixture replacement in student bathrooms - COMPLETED SUMMER 2018
  • Remove old, built-in cafeteria tables with new circular tables - COMPLETED SUMMER 2018
  • New classroom furniture purchased with Instructional Upgrades bond money - COMPLETED SUMMER 2018

Building Systems / Safety & Security

  • Improve cafeteria/kitchen plumbing components - COMPLETED SUMMER 2018
  • Replace deteriorating sewer system components - COMPLETED SUMMER 2018
  • Upgrade building power components to minimize building power loss and associated learning disruptions - COMPLETED SUMMER 2018
  • New electronic card readers for safe and secure building access - COMPLETED SUMMER 2018
  • New exterior and interior digital security cameras - COMPLETED SUMMER 2018
  • Improvements to staff lounge eletrical outlets - COMPLETED SUMMER 2018

School Grounds

  • New fence around school playfield - COMPLETED SUMMER 2018
  • Drainage improvements to eliminate playground flooding - COMPLETED SUMMER 2018
  • Construction of new preschool playground - COMPLETED SUMMER 2018

Early Childhood Education

  • Construction of new preschool playground - COMPLETED SUMMER 2018

Renovations & Remodels

  • Installation of stage curtain - COMPLETED SUMMER 2018
  • Add pottery kiln room with kiln - COMPLETED SUMMER 2018
  • New ventilation system for art kiln room - COMPLETED SUMMER 2018
  • Replace gym/stage partition with new moveable partition - COMPLETED SUMMER 2018

Instructional Upgrades

  • Mounted digital projectors and classroom audio systems in the majority of building classrooms as well as purchase of new classroom furniture

*Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.