Project rating - 3 $2.1-$2.5M
Project rating - 3

Planning/Design - Now the fun begins! Adams 12 Five Star Schools' business services team, in collaboration with the school community, are planning and designing the logistics for the individual projects of your school's investment plan.

Latest Updates

Stukey Elementary will receive significant renovations and improvements in Summer 2018 as part of the 2016 Bond Program.

These planned improvements are part of building system, infrastructure and safety upgrades identified during the bond development process as well as a Design Advisory Group (DAG), of school staff, parents and community members who worked with the architectural team in Spring 2017 to prioritize a scope of renovation and remodel work. As part of this process, DAG members identified a list of primary and secondary priorities for the expenditure of money from the school's renovations and specials bond budget. This did not include money already designated for identified critical deferred maintenance needs and safety and security upgrades.


Construction Start Year(s) 

2017: Design Work
*Some minor improvements, including work related to instructional upgrade purchases, may occur during 2017.

2018: Major construction expected to take place in Summer 2018 with anticipated completion for the start of the 2018-19 school year.


Project Team

ArchitectCuningham Group Architecture

Construction Manager/General Contractor: Adolfson & Peterson Construction


The majority of the following improvements are expected to take place at Stukey Elementary in Summer 2018:

Building Structure

  • New tubular daylighting devices in classrooms and library
  • Exterior classroom window replacement throughout building
  • Add windows to cafeteria (currently no windows)

Building Interiors

  • Replace failing moveable partitions in classrooms with permanent walls
  • Remove failing rubber flooring in gym with district standard poured-in-place flooring
  • Replace failing flooring in school corridors and bathrooms
  • Painting of corridor door frames and panels (located above doors)
  • Painting of cafeteria walls
  • Remove abandoned classroom unit ventilators to allow more teaching space

Equipment & Furnishings

  • Replace kitchen grease interceptor
  • Fixture replacement in student bathrooms
  • Remove old, built-in cafeteria tables with new circular tables

Building Systems / Safety & Security

  • Improve cafeteria/kitchen plumbing components
  • Replace deteriorating sewer system components
  • Upgrade building power components to minimize building power loss and associated learning disruptions
  • New electronic card readers for safe and secure building access
  • New exterior and interior digital security cameras
  • Improvements to staff lounge eletrical outlets

School Grounds

  • New fence around school playfield
  • Drainage improvements to eliminate playground flooding
  • Construction of new preschool playground

Early Childhood Education

  • Construction of new preschool playground

Renovations & Remodels

  • Installation of stage curtain
  • Add pottery kiln room with kiln
  • New ventilation system for art kiln room
  • Replace gym/stage partition with new moveable partition

Instructional Upgrades

  • Mounted digital projectors and classroom audio systems in the majority of building classrooms

*Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.