Bond Newsletter - February 2018

Submitted on Thu, 03/01/2018 - 12:06pm

 

Work nears peak level on new Thunder Vista P-8

Construction about 65 percent complete on school scheduled to open in August


STEM Lab staff tours new building renovation, addition

With the first phase of construction on STEM Lab in Northglenn now past the halfway mark, school teachers and staff got an up-close look at the construction during a recent tour.

The school is in the midst of a multi-phased, $20 million renovation that will transform the 47-year-old building into a state-of-the-art learning environment for more than 700 students from across the district.

Start of steelwork planned for Arapahoe Ridge expansion in March

March will be a big month for the ongoing expansion of the Arapahoe Ridge Elementary in Westminster.

According to the current construction timeline, steel work on the 18,000-square-foot expansion is scheduled to begin about mid-March. The start of construction on the addition's steel skeleton marks a major milestone in project.

Cotton Creek construction accelerates in February

Site challenges that slowed initial progress on the Cotton Creek expansion were left behind in February as construction accelerated on the project.

Drilling and pouring of foundational caissons finished in February, which allowed work to begin on the preparation and pouring of concrete grade beams and foundation walls for the Westminster school's 14,000-square-foot addition.

Community Board of Education meeting to focus on bond progress

Parents and community members are invited to join the Adams 12 Five Star Schools Board of Education meeting at 7 p.m., Wednesday, March 7, at Northglenn High School.

The meeting will include a presentation from the Long Range Planning Advisory Committee (LRPAC) on the 2016 Bond Program, a discussion about the district's ELEVATE strategic planning and information about a potential state school funding ballot measure.

Look for the 2016 Bond Program community update headed to your mailbox

Want to know everything that's taken place since the community supported the Adams 12 Five Star Schools bond question in November 2016? Interested in what's still ahead in your school or community?

Look for the 2016 Bond Program Community update headed to your mailbox in early March.

  • Horizon High School Design Advisory Group Meeting
    2 to 3:30 p.m., Wednesday, Feb. 28, 2018
    Horizon High School,  5321 E. 136th Ave., Thornton, CO 80602
  • Coffee with the Thunder Vista P-8 Principal
    9 to 10 a.m., Friday, March 9, 2018
    Parkside Community Center, Broomfield
  • Long Range Planning Advisory Committee Meeting
    9 to 10:30 a.m., Thursday, March 15, 2018
    Educational Support Center,  1800 E. 128th Ave., Thornton, CO, 80241

 

Recent News

Look for the 2016 Bond Program headed to your mailbox

Tuesday, February 20, 2018 - 2:45pm

Publication updates community on investment in district schools, facilities

Want to know everything that's taken place since the community supported the Adams 12 Five Star Schools bond question in November 2016? Interested in what's still ahead at your school or your community?

Look for the 2016 Bond Program Community update headed to your mailbox in early March. The publication includes updates on:

Bond construction projects currently under way Projects ...

First phase of STEM Lab renovation rushes toward finish line

Friday, March 30, 2018 - 9:00am

Community meeting planned to update parents, community on progress

The two-year renovation and reconstruction of STEM Lab is by all definitions a marathon, not a sprint but, as phase one of the project nears completion, construction is reaching a frenetic pace.

Over the past month, masonry work on the exterior of the building's 25,000-square-foot east expansion has surpassed the halfway complete mark. Inside the building - both new and existing - ...