Bond Newsletter - July 2017

Updated on Thu, 08/31/2017 - 3:43pm

July 2017

District enlists industry partners to envision new career training programs
school building

New P-8 school continues to take shape

With another month of construction finishing, the structure continues to emerge from the ground for the new P-8 school in the Anthem community of Broomfield.

The most noticeable site development in July was the construction of the first of the school’s three 45-foot stair towers. Concrete foundation work also continued as the outline of the 142,000 square-foot school becomes more defined. Foundation work is expected to wrap up in mid-August.

 
school building

Name, mascot needed for new school

Adams 12 Five Star Schools is building its first new school in more than a decade and needs the public’s help to name it.

The new 142,000-square foot school is currently under construction in the Anthem community of Broomfield. The school is expected to open in Fall 2018 and will eventually be home to more than 900 preschool through eighth-grade students.

Click to read more about how you can become involved in the naming process.

stem lab building

STEM Lab construction rolls forward

The STEM Lab reconstruction and renovation is no ordinary construction project.

Not only does it involve a meticulous, phased two-year process to transform a 46-year-old school building into a 21st-Century STEM learning facility but a majority of the work will take place as nearly 500 students and staff members continue to work and learn.

So, as construction accelerated in July inside and outside the school, the focus was also on preparing to welcome staff and students back in August.

stem lab building

JHL Constructors to build school expansions

Adams 12 Five Star Schools has selected a general contractor to build two major school expansion projects scheduled to begin in early 2018.

Centennial-based JHL Constructors was selected through a competitive RFP process to build a 12-classroom expansion at Arapahoe Ridge Elementary in Westminster and an 8-classroom expansion at Cotton Creek Elementary, also in Westminster. As promised in the 2016 Bond Program, the building expansions will allow both schools to remove modular student classrooms. Arapahoe Ridge will also expand educational opportunities with a preschool program.

First Day of School - All Elementary Students K-8
Wednesday, 08/16/2017
First Day of School - All Students K-12
Thursday, 08/17/2017
 

Recent News

Look for the 2016 Bond Program headed to your mailbox

Tuesday, February 20, 2018 - 2:45pm

Publication updates community on investment in district schools, facilities

Want to know everything that's taken place since the community supported the Adams 12 Five Star Schools bond question in November 2016? Interested in what's still ahead at your school or your community?

Look for the 2016 Bond Program Community update headed to your mailbox in early March. The publication includes updates on:

Bond construction projects currently under way Projects ...

First phase of STEM Lab renovation rushes toward finish line

Friday, March 30, 2018 - 9:00am

Community meeting planned to update parents, community on progress

The two-year renovation and reconstruction of STEM Lab is by all definitions a marathon, not a sprint but, as phase one of the project nears completion, construction is reaching a frenetic pace.

Over the past month, masonry work on the exterior of the building's 25,000-square-foot east expansion has surpassed the halfway complete mark. Inside the building - both new and existing - ...