2016 Bond Program News Articles

Snow, cold don't slow STEM Lab progress [w/video]

Wednesday, February 27, 2019 - 1:45pm

Exterior brick work wraps up as interior construction pushes ahead

Despite an often cold and snowy month, the ongoing STEM Lab renovation and reconstruction rolled ahead in February with much of the work shifting toward interior work on the building's second 25,000-square foot expansion.

Construction is quickly approaching the final sprint of a two-year marathon to transform the aging 47-year-old middle school into a state-of-the-art learning facility ...

Community input needed in CTE branding effort

Thursday, February 28, 2019 - 11:45am

District looks to link CTE through shared name, colors, core values

With Career and Technical Education (CTE) opportunities poised to expand over the next two years in the Five Star District, community members are being asked to provide their input on a new brand for the district’s career-focused education programs.

In April 2018, the district formed a CTE Brand Steering Committee of CTE administrators and educators from across the district to study ...

Interior, exterior work continues on STEM Lab [video]

Friday, January 18, 2019 - 2:30pm

School remains on schedule for August completion

As a new calendar year began, interior work on the second of two, 25,000-square-foot expansions to the building got under way as exterior work continued.

By mid-January, the new main entry to the building was being framed, providing a look at the final shape of the building. Exterior brick work was more than a quarter complete with much of the building wrapped in a thick sheet of ...

On schedule STEM Lab project moves ahead in December [video]

Tuesday, December 11, 2018 - 1:45pm

Interior work on building expansion to begin soon

Construction on the reconstructed STEM Lab in Northglenn moved ahead in December and remains on pace for an August 2019 completion.

The school is in the midst of a two-year renovation and reconstruction. Phase 2, which began this past summer, involves the construction of a 25,000-square-foot expansion on the west side of the building. A similar expansion was completed on the east side ...

District completes sale of second and final set of bonds

Tuesday, December 11, 2018 - 10:30am

Money will support later phases of bond program improvement work

Adams 12 Five Star Schools has completed the planned second and final sale of general obligation bonds as part of the successful passage of a $350 million bond program approved by the Five Star community in 2016.

The sale of $65 million in bonds was completed Nov. 28, 2018, and will support later phases of school and facility improvement work planned as part of the five-year bond ...