Thunder Vista P-8 in Broomfield

3461 Preble Creek Parkway, Broomfield, CO 80023 - Website
Anthem School Renderings
Project rating - 0 $31M - 36.5M
Project rating - 0

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

Construction on Thunder Vista P-8 in the Anthem community of Broomfield began in April 2017. The school is scheduled to open in August 2018 and is projected to eventually serve 900 K-8 students and 128 preschool students.

March Highlights

  • Continued drywall installation 
  • Continued finish work (tile, paint, polished concrete flooring)
  • Installation of basketball hoops and divider curtain in gym
  • Construction of gathering stair above large commons area and pouring of steps
  • Continued window installation
  • Continued exterior brick veneer work
  • Delivery of kitchen equipment
  • Paving of upper school parking lot
  • Classroom casework installation begins
  • Exterior site work (playgrounds, upper parking lot paving, irrigation water line installation)

Looking ahead to April

  • Start of elevator assembly 
  • Start of carpet installation
  • Start of installation of gym floor
  • Drywall installation continues
  • Exterior brick work continues
  • Continued exterior site work and landscaping (playground, irrigation water line installation)

News Updates

Thunder Vista gets unique touches with building finish work - March 2018

Construction nears peak on Thunder Vista P-8 - February 2018

Construction on Thunder Vista P-8 keeps pace in January - January 2018

Families of new school give final steel beam proper send-off - December 2017

Thunder Vista construction passes quarter completion mark - November 2017

Flurry of construction activity at Thunder Vista P-8 - October 2017

New school in Broomfield to be named Thunder Vista P-8 - September 2017

Steel, concrete work continue on Thunder Vista P-8 - September 2017

Steel work signals new phase of P-8 construction - August 2017

Parents invited to be part of P-8 Base Camp - August 2017

Name, mascot suggestions needed for new P-8 school - August 2017

New P-8 school continues to take shape - July 2017

First walls going up at new P-8 school in Anthem  - June 2017

P-8 school construction trudges on through wet weather, mud - May 2017

Ground broken on new P-8 school - April 2017

Principal named for new Anthem school - April 2017


Project Team

ArchitectHord Coplan Macht

Construction Manager/General ContractorAdolfson & Peterson Construction


New P-8 School in Anthem Groundbreaking Video 2017