North Mor Elementary School

9580 Damon Drive, Northglenn, CO, 80620 - 720-972-5540 - Website
North Mor Building 2016
Project rating - 3 $2.2-$2.6M
Project rating - 3

Planning/Design - Now the fun begins! Adams 12 Five Star Schools' business services team, in collaboration with the school community, are planning and designing the logistics for the individual projects of your school's investment plan.

Latest Updates

Planned renovations for North Mor Elementary are currently in the Design Development phase. During this phase, drawings and other presentation documents are created to further define the design concept and describe it in terms of architectural, electrical, mechanical, and structural systems. A probable project cost is also established during this phase.

In August 2017, Adolfson & Peterson Construction (AP) was selected as the CMGC (Construction Manager / General Contractor) for this project. Prior to completing this work, they will partner with the project design team, Cuningham Group Architecture, to help ensure that scope and budget goals for the project are met. Construction and renovation work is expected to take place in Summer 2018.

A Design Advisory Group (DAG), of school staff, parents and community members, worked with the architectural team in Spring 2017 to define the preliminary scope of potential renovation and remodel work. As part of this process, DAG members established a list of primary and secondary priorities for the expenditure of money from the school's renovations and specials bond budget. This did not include money already designated for identified critical deferred maintenance needs and safety and security upgrades. You can review DAG meeting minutes below:

North Mor Elementary Design Advisory Group Meeting Minutes - May 16, 2017

North Mor Elementary Design Advisory Group Meeting Minutes - April 21, 2017

Construction Start Year(s) 

2017: Design Work
*Some minor improvements, including work related to instructional upgrade purchases, may occur during 2017.

2018: Major construction expected to take place in Summer 2018 with anticipated completion for the start of the 2018-19 school year.

2022: Roof replacement 

Project Team

Architect: Cuningham Group Architecture

Construction Manager / General Contractor: Adolfson & Peterson Construction 

Building Structure

  • Replace roof

Building Interiors

  • Replace failing flooring in critical locations

Equipment & Furnishings

  • Replace stage partitions

Building Systems / Safety & Security

  • Improve cafeteria/kitchen plumbing components
  • Replace deteriorating sewer system components
  • Replace failing water heater and storage tanks
  • Replace failing water lines
  • Upgrade heating and cooling systems for efficiency and more consistent temperature control for comfort
  • Install electronic card access to promote a safe and secure building
  • Install digital security camera system

Renovations & Remodels

  • Remodel priority items, such as ceilings, walls, floors, windows, doors, painting upgrades, paving restoration, lunch rooms, classrooms and bathrooms *Significant Renovation
  • Repair or replace specials (music, art, gym) program components such as wall panels, ceiling tiles, flooring and program specific equipment 

Instructional Upgrades

  • Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.

    *Timeline for Instructional Upgrades is dependent on the specific upgrades selected by our school community. More information to follow.