Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

Current Construction Activities

  • The exterior “skin” of the 25,000 square-foot east expansion is complete. Construction workers have begun exterior brick work. Windows have also arrived for the new building and installation was set to begin on those in January.
  • The new addition’s roof is complete and this allowed the final heating and air conditioning units to be hoisted into their final place in early January.
  • Over the winter break, new gas lines as well as a new electrical transformer were installed. These were expected to be turned on over the long President’s Day weekend in February.
  • In the existing east wing, renovation work is ongoing. The reconstructed locker rooms were expected to be completed for student use by the end of January.

News Updates

Construction moves briskly on STEM Lab renovation - January 2018

With STEM Lab expansion steel in place, exterior framing begins - November 2017

Steel goes up for STEM Lab expansion - October 2017

Steady progress on STEM Lab renovation and expansion - August 2017

STEM Lab construction rolls forward - July 2017

Demolition work paves way for STEM Lab renovation, expansion - June 2017

Students help break ground on STEM Lab renovation - May 2017

STEM Lab Groundbreaking Video

Construction Start Year(s) 

Phase 1 - June 2017 - May 2018: Build new east wing. Renovate portions of existing east wing. Phase 1 Classroom Plan
The construction area for Phase 1 of this project will require the use of the existing playground area. STEM Lab students will utilize the adjacent city of Northglenn park for recess activities. Student pick-up and drop-off areas will not be impacted by the first phase of construction. (See Phase 1 Site Logistics Plan at bottom of page)

Phase 2 - June 2018-May 2019: Demolish existing west wing. Build new west wing. Phase 2 Classroom Plan

Project Team

Architect3980 Design

Construction Manager/General ContractorAdolfson and Peterson Construction